Yamagata Prefecture: Equipment Rental
Expansion of new production line and scrap and build (S&B) of existing facilities
A customer needed to upgrade their plant facilities, due to the urgent need to double production volume in the current year.
As production facilities were relocated from another plant, the expansion of the facilities was ミラクルカジノ 出金条件mpleted in a short time. There was, however, a lack of pure water required for the production facilities. The customer decided to quickly procure a pure water system, but due to the time it would take to deploy such a system (3 months), they chose to rent the PUREBOX system in order to start production.
Sector | Electronic ミラクルカジノ 出金条件mponents |
---|---|
Capacity | 5 m3/h × 2 units |
Duration | 3 months |